Project data

  • Customer
  • Carmel School / Kellett School
  • Value
  • $40,000,000
  • Area
  • 50,000 sq ft
  • Form of contract
  • Management contractor
  • Programme duration
  • 16 weeks
  • Completion date
  • September 2009

Overview

ISG delivered the upgrade and refurbishment of a shared campus for Carmel & Kellett Schools. The existing building had been abandoned for approximately seven years prior to commencement of refurbishment, therefore requiring a total replacement of windows, building services, structural repairs, and outdoor sports ground reconstruction as well as converting the hall into a gymnasium and 500-seat auditorium. The school consists of 50,000 sq ft floor area across six floors, with facilities such as laboratories, design & technology classrooms, libraries, music room, caretaker’s facilities and an auditorium.