Project data

  • Customer
  • WestLB Bank AG Hong Kong
  • Area
  • 30,000 sq ft
  • Programme duration
  • 3 months
  • Completion date
  • February 2009

Overview

In November 2008, ISG was appointed as the main contractor for WestLB Bank’s new office fit out and relocation project at Citibank Tower and ICBC Tower in Central, HK.

Focus was placed on the acoustic performance for meeting rooms and the dealing room. Despite a technical issue, insufficient essential power supply from the base building for phase 1, which created some pressure against the project schedule, the whole project was completed successfully in three different phases: Phase 1 for the server room; Phase 2 for the office area which included dealing area, reception, pantry, and manager/conference rooms; and Phase 3 for reinstatement of the existing office which was completed by February 2009.